● __(71)__ techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .
(71)A. Schedule forecasts
B. Schedule compression
C. Change requests
D. Data analysis
● Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by __(72)__.
(72)A. negotiation
B. the court
C. lawyer
D. arbitration
● The organization shall undertake change in a planned and systematic manner, taking account of the review of the potential consequences of changes and taking action as necessary, to ensure the integrity of goods and services are maintained. This is called ( ).
(73)A. control of changes
B. control of plans
C. control of accounts
D. control of service
● Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved ( ).
(74)A. schedule baseline
B. cost baseline
C. cost output
D. cost input
● The top management of a company will review the organization’s management system, the management review will include consideration of :
( a ) customer feedback on quality
( b ) processes performance and product conformity
The purpose of management review is ( ).
(75)A. control of customers
B. control of measurements
C. control of qualities
D. control of opportunities
课课家教育专注软考培训10年以上,一直坚持自主研发,将丰富的软考培训经验有效融入教程研发过程,自成体系的软考视频教程、软考培训教材和软考在线题库,使考生的学习更具系统性,辅导更具针对性。想要报考2018年软考的考生现在就可以开始备考了,报名课课家软考各科目考试赠送:辅导教材、历年真题、考前冲剌资料、论文模版(高项)、在线模拟测试题库、老师专属答疑指导等,以保障学员顺利通过考试。
>>>>>>点击进入软考报名专题
>>>>>>2018下半年信息系统监理师上午真题汇总
共93节 · 35小时40分钟套餐优惠
¥299.001398人在学
共19节 · 33小时6分钟套餐优惠
¥399.003702人在学
共103节 · 55小时58分钟
¥699.00128036人在学
共102节 · 29小时53分钟
¥298.0036634人在学